Inside the spire: Zenith S.A.S at Glasgow Cathedral

Zenith S.A.S is a framework contractor with Historic Environment Scotland and was approached to provide external scaffolding at Glasgow Cathedral so that repairs could be carried out to the top of the spire and the bottom level windows replaced.

The scaffold was designed so both jobs could run at the same time and so the client's contractor could remove and replace internal steelwork while they did. What it could not account for was what inspections of the spire would find.

A change of scope

Detailed inspections identified extensive corrosion in the internal steelwork, well beyond initial expectations. The steel cross tree members were so heavily corroded that substantial repairs to the internal structure were needed, and a full height internal scaffold was required to support the replacement works.

Zenith produced a complete redesign and a revised material schedule within two weeks, and the client's programme continued without delay.

Designing for a scheduled monument

The cathedral's status as a scheduled monument ruled out conventional anchorage, so there were no intrusive ties. Stability came instead from continuous plan bracing, butt tube arrangements, and non-invasive window and box ties where they were available, giving global stability without compromising the historic stonework.

Internally there was a different problem. The base of the spire sits on timber construction and could not accommodate significant imposed loads. The internal scaffold was engineered to transfer loads across four discrete levels, using beam arrangements positioned at existing window openings, which eliminated point loading at low level while keeping the support system fully independent.

The spire gave the design team a continuously tapering profile to follow, with offsets, decorative stone courses, buttresses and pinnacles. The scaffold stepped in at four levels, and load paths were managed through reverse pick-up arrangements so forces were distributed between inner and outer standards as the footprint reduced. At an elevation of around 68 metres, wind loading was a critical design consideration.

The design phase included a detailed site survey alongside a review of historical drawings and calculations.

The build

Erection took three months and followed a clearly defined engineered sequence. The external scaffold went up first, starting at the tower wall head, where the initial materials were craned into position to establish the base working platform.

A cantilevered loading bay was installed at an early stage, which transformed the logistics strategy by enabling all subsequent materials to be lifted directly to the working level. This allowed the scaffold to be erected continuously without relying on internal access routes and kept it fully segregated from the operational cathedral below. 

Tube schedules were planned in advance and members cut to precise lengths at ground level before installation, reducing manual handling at height and holding dimensional accuracy as the scaffold followed the tapering geometry. Lightweight aluminium tube made handling faster and reduced operative fatigue.

Internal standards were progressed ahead of the external lifts in stages of three to four lifts, with structural beams introduced at levels 3, 6 and 10 to support ongoing erection and load transfer.

The work was delivered by a team of 12 scaffolders, many of them multi-skilled in rope access.

Keeping the cathedral open

The cathedral remained open throughout, hosting visitors, services and events, so a fully segregated logistics strategy was put in place. All materials were craned directly onto the purpose-designed cantilevered loading bay from a controlled rear compound, which eliminated the need to transport anything through public or internal areas and significantly reduced the interface risk between operatives and the public.

A cantilevered external staircase replaced traditional ladder access, improving safe movement for operatives, inspectors and the client's team. A goods hoist and monorail system handled vertical and horizontal transfer of materials directly to active workfaces. Wide working platforms throughout gave sufficient space for masonry, steelwork and conservation activities to be carried out safely alongside one another.

Other safety features included advanced guardrail systems, ladder access gates and debris netting, with stability engineered throughout using non-invasive restraint methods. A fantastic project. 